One of our blog subscribers requested advice on force majeure under the FIDIC Red or Yellow books. The good news is that the FIDIC force majeure clauses are nearly the same under the Red, Yellow, Silver, and Gold forms of contract, so the following is applicable to all of them.

Sub-Clause 19.1 (Definition of Force Majeure) the Red Book states that:

‘In this Clause, “Force Majeure” means an exceptional event or circumstance:     
(a) which is beyond a Party’s control,     
(b) which such Party could not reasonably have provided against before entering into the Contract,     
(c) which, having arisen, such Party could not reasonably have avoided overcome, and     
(d) which is not substantially attributable to the other Party.’

Thus, to qualify as a force majeure event, it has to tick all of the boxes (a) to (d) above.

The clause, however, goes on to offer further definitions as follows:

Force Majeure may include, but is not limited to, exceptional events or circumstances of the kind listed below, so long as conditions (a) to (d) above are satisfied:
(i) war, hostilities (whether war be declared or not), invasion, act of foreign enemies,     
(ii) rebellion, terrorism, revolution, insurrection, military or usurped power, or civil war,     
(iii) riot, commotion, disorder, strike or lockout by persons other than the Contractor’s Personnel and other employees of the Contractor and Sub-contractors,     
(iv) munitions of war, explosive materials, ionising radiation or contamination by radio-activity, except as may be attributable to the Contractor’s use of such munitions, explosives, radiation or radioactivity, and     
(v) natural catastrophes such as earthquake, hurricane, typhoon, or volcanic activity.’

So, not only does it have to meet the above requirements (a) to (d), but the event should also be ‘of the kind listed’ above.

If a force majeure event does occur and either party is prevented from performing its obligations, then the party affected is obliged to give the other party notice under Sub-Clause 19.2 (Notice of Force Majeure).

You will note that Sub-Clause 19.1 (Definition of Force Majeure) does not specify any remedy or entitlement in the case that a force majeure event occurs. For this we must look to Sub-Clause 19.4 (Consequences of Force Majeure), which states that:

‘If the Contractor is prevented from performing any of his obligations under the Contract by Force Majeure of which notice has been given under Sub-Clause 19.2 (Notice of Force Majeure), and suffers delay and/or incurs Cost by reason of such Force Majeure, the Contractor shall be entitled subject to Sub-Clause 20.1 (Contractor’s Claims) to:
(a) an extension of time for any such delay, if completion is or will be delayed, under Sub-Clause 8.4 (Extension of Time for Completion), and
(b) if the event or circumstance is of the kind described in sub-paragraphs (i) to (iv) of Sub-Clause 19.1 (Definition of Force Majeure) and, in the case of sub-paragraphs (ii) to (iv), occurs in the Country, payment of any such Cost.’             

Consequently, the Contractor would be entitled to an extension of time if the event delayed the completion date. He would also be entitled to additional payment, but only under certain circumstances. The circumstances entitling the Contractor to additional payment are defined by reference back to Sub-Clause 19.1 (Definition of Force Majeure) where we will see that:

The event must have occurred in the Country where the Permanent Works are to be executed and

Natural catastrophes such as earthquake, hurricane, typhoon or volcanic activity’ are excluded

Consider the following: a claim for an extension of time and additional payment has been submitted by a contractor under the force majeure provisions when the police closed the project Site down for security reasons during a political conference that took place in a hotel across the road from the Site. Do you think that this comprises a qualifying event?

Leave a comment below with your opinion on whether the above scenario qualifies under FIDIC force majeure provisions and why or why not.

This blog was written by ICCP Executive Officer and Fellow, Andy Hewitt

If you would like to learn more about claims, check out our training partner, Claims Class.

Enjoying the ICCP’s articles? Why not sign up to our mailing list and receive new articles straight into your mailbox. Or, want access to a library of members-only content on contracts and claims, check out our Membership page and join the ICCP community today.

Privacy Preference Center