The global hot topic this month seems to be the coronavirus and my consultancy practice has received lots of questions from clients so today, we thought we’d take a look at some of those questions and share our thoughts with you.
The usual question we are asked is:
“We are obtaining labour/materials/plant/equipment from China and the supply is being delayed. Are we entitled to claim for an extension of time and additional costs?”.
Our answers, as usual, have been along the lines of “it depends on your particular contract, but possibly”.
I know that this is a bit of a lawyer’s answer, but it really does depend on several things. Let’s however, have a look at what the FIDIC Red and Yellow Books, 1999 Editions, have to say on the subject.
Firstly, Sub-Clause 8.4 (Extension of Time for Completion) provides that an extension of time is warranted in the case of ‘Unforeseeable shortages in the availability of personnel or Goods caused by epidemic or governmental actions…’. This seems to provide a fairly clear entitlement to an extension of time, but not the payment of costs.
Secondly, FIDIC also possibly provides entitlement to an extension of time under Sub-Clause 19.4 (Consequences of Force Majeure). This is however arguable because to be considered as a force majeure event, the conditions contained in Sub-Clause 19.1 (Definition of Force Majeure) must be satisfied and it is not certain that they are. Undoubtedly, there is enough uncertainty here to anticipate a strong defensive argument from the other side of the fence, so a persuasive argument must be included in any claim.
Sub-Clause 8.4 (Extension of Time for Completion) does not provide entitlement to the payment of Costs, so the matter of Costs is dependent on the virus being considered as a force majeure event. Even if agreement is reached about the virus being a qualifying event, there is however another hurdle to overcome because Sub-Clause 19.4 (Consequences of Force Majeure) requires the event to have occurred in the Country. “The Country: is defined in FIDIC as ‘the country in which the Site (or most of it) is located, where the Permanent Works are to be executed.’ So, it seems that, unless the project is in a country where the virus has occurred and has a direct effect, then Costs may not be awarded. Once again, there, may be an argument if the government of the country has introduced measures that have affected the project.
There are of course other considerations to be made before a claim is justifiable, some of these include:
- How has the virus affected the Contractor and his subcontractor’s activities?
- What activities have been or are likely to be delayed?
- Are the affected activities on the critical path?
- Can the effect of the delays be demonstrated to predictably have an effect on the Time for Completion?
- Have appropriate notices been given in a suitable format?
- Does the Contractor have contemporary records to substantiate and ascertain the effects of the delays?
All of the above, of course, is just good professional practice when it comes to investigating and preparing claims, but it’s surprising how many contractors fail to comply and then wonder why their claims are rejected or, at best, take a long time to resolve.
This blog was written by ICCP Executive Officer and Fellow, Andy Hewitt. Andy has also written a detailed paper for members that discusses COVID-19 in relation to the FIDIC 1999 contracts (Red and Yellow Books). If you’re an ICCP member, please login to the Member’s Area to download.
If you would like to learn more about claims, check out our training partner, Claims Class.
Enjoying the ICCP’s articles? Why not sign up to our mailing list and receive new articles straight into your mailbox. Or, want access to a library of members-only content on contracts and claims, check out our Membership page and join the ICCP community today.
well explained
Silver book I think has only the Clause 19 [Force Majeure] provisions. Don’t forget the express duty to minimise the delay no mention of costs costs.
The Virus I thin would fit the description of Sub-Clause 19.1 [Definition of Force Majeure]
In this Clause “Force Majeure” means an exceptional event or circumstance:
which is beyond a Party’s control,
which such Party could not reasonably have provided against before entering into the Contract,
which, having arisen, such Party could not reasonably have avoided or overcome, and
which is not substantially attributable to the other Party.
When giving the notice you need to be crafty about what you actually call the event or circumstances as time may have slipped beyond 14 days for the virus in China. But and action of the Government of Italy for example may be in time.
What if the effect of the FM is controlled by the Party (i.e government authority) and they ask for precautionary measures, close borders, etc.?
In relation to this explanation, if the Contractor is awarded with EOT, but not additional cost, which index is applicable for price adjustment, “index of the extended period” or “index at the end of the original contract period”?
My opinion Coronavirus is global pandemic and it is neutral event in JCT form of contract which means nobody cause this event.
Under Contract it is entitlement for Contractor to claim EOT due to Force Majeure.
If Contractor raise up monetary claim on this event as a reason. It shall not fall within Contractual element whereby I believe shall only via common law channel to claim on his entitlement and again it is not straight and easy way on this monetary claim.
Thank you
Hi Tsmok,
Thank you for your opinion on the JCT contacts.
As we said in the blog article, everything depends on the provisions of the actual contract.